MANUAL READERS: New developers, construction management, general contractors, and office staff. Junior project managers, junior inside and outside superintendents, site coordinators, subtrade foremen/women, and journeypersons who want to move up. Construction management and project management students. Schedule for lean webinars coming soon.
Table Of Contents
PRE-CONSTRUCTION
1.0 Physical site review.
1.1 Detailed review checklists.
Architectural drawing review.
Structural drawing review.
Mechanical drawing review.
Electrical drawing review.
Landscape drawing review.
Review list for shop drawings.
All of the above to be completed during or before excavation by
consultants, subtrades, and superintendent. This will drastically
cut down on future requests for information.
1.1a Daily construction photo documentation and benefits.
1.1b Bridget construction management mobile app.
1.2 List of suppliers and subtrade meetings to be completed during or before excavation by superintendent.
1.2a Importance of jobsite information flow. Critical path.
1.2b Lean A3 construction problem-solving.
1.3 Work breakdown structure.
1.3a Weekly pull planning.
1.3b Jobsite involvement in construction ergonomics makes good sense.
1.3c On-site and off-site trade prefab.
1.3d Keep jobsite trade teams cooler and warmer.
EXCAVATION AND SHORING
2.0 Excavation and shoring start-up.
2.1 Daily cycles and procedures with extreme weather protocols.
PARKADE FORMING
3.1 Excavation hole and forming organization.
3.2 Shotcrete walls, single-sided and two-sided.
3.3 Other forming system advantages.
3.4 Critical path, early stripping of electrical room and why.
3.5 Parkade slab, pre-pour, during pour, and post-pour checklists,
4.0 CRANE ERECTION
4.1 Pre-erection requirements.
4.2 Pre-operation requirements.
4.3 Pre-climbing requirements
4.4 Pre-dismantling requirements.
4.5 Rigging.
5.0 TOWER FORMING AND SEQUENCING
5.1 Street level.
5.2 Storage.
5.3 Fly form building.
5.4 Five- to six-day forming and subtrade sequencing for typical slabs.
5.5 Accelerated roof completion.
6.0 FLEXIBLE LEAN OFFICES
Move to best tower locations, very important.
6.1 Importance of bi-weekly injury and incident-free meetings by superintendent in addition to weekly safety meetings.
7.0 EXTERIOR MAN-LIFT ERECTION
7.0 General prep and erection.
7.1 Daily effective man-lift use and sequencing deliveries. Critical path.
7.2 Man-lift takedown.
SUPERINTENDENTS INTERIOR SEQUENCING
8.0 Upper tower floor rain diversion during interior rough-in and finishing.
8.0a Plumbers’ drainage and cast.
8.1 Window prep, install, and handover.
8.2 Steel stud layout, erection, drop ceilings, con-flow, and handover.
8.3 Mechanical rough-in and pre-drywall handover.
8.4 Electrical rough-in and pre-drywall handover.
8.5 Backing, fire caulking install, and pre-drywall handover.
8.6 Floor levelling.
8.7 Pre and post spray and rigid insulation install.
8.8 Drywall delivery, install, mudding/taping, and pre-paint.
8.8a Temporary heating suites.
8.9 Paint application and pre-door delivery handover.
8.10 Finishing carpenters install of door frames, doors, door trim, window stools, and selective baseboard for pre-paint.
8.11 Pre-painter spray out. Doors, trim, and window stool.
8.12 Kitchen cabinet delivery, install, and post-install.
8.13 Tile delivery, install, floor and wall sequencing. Post-install.
8.14 Electrician lighting, switches, and plugs.
8.15 Countertop delivery, install and post-install.
8.16 Backsplash install.
8.17 Shower glass and door install.
8.18 Flooring delivery, install, and post-install.
8.19 Appliance delivery, install and post-install.
8.20 Plumber finishing and post-install.
8.21 Electricians’ final pass-through and final.
8.22 Shelving and finishing carpenters final pass-through.
8.23 Final window, balcony slider and balcony exterior door final adjustments.
8.24 Final painter pass-through.
8.25 Protection removal sequencing by well-trained on-site personnel or cleaners.
8.26 First clean of suites.
8.27 Blind install and post-inspection.
8.28 Schedule marketing department walkthrough and key handover.
8.29 Complete second clean pre-home owner walkthrough final.
8.30 Home owner’s first suite inspection.
8.31 Third clean just before move-in day.
8.32 Electrical closets and communication closets.
8.33 Timesavers. Accessories, tools, and simple ways to improve jobsite productivity.
8.34 Penthouse interior and exterior completion.
ELEVATOR DELIVERY, STORAGE, PRE- CONSTRUCTION START-UP AND INSTALL SEQUENCING FINAL.
9.0 Delivery, storage and pre-install.
9.1 Sequence of install.
9.2 Pre-section 5 checklist and pre-final.
9.3 Final.
10.0 INTERIOR COMMON AREAS / LOBBY ROUGH-IN AND FINISHING REVIEW.
10.1 Interior common area rough-in and finishing.
10.2 Main lobby area rough-in and finishing.
10.3 Man lift suites catch-up sequencing.
OUTSIDE TOWER SEQUENCING AND FINISHING
11.0 Roof prep and completion.
11.1 Balcony liquid membrane.
11.2 Window wash anchors and window washing safety.
11.3 Shared exterior swing stages for multiple trade use recommended and why.
11.4 Railing delivery, install, and final.
11.5 Flashing, window, parapet review, and sign-off.
PARKADE SEQUENCING, SHORING STRIPPING THROUGH TO LINE PAINTING
12.0 Stripping, concrete remediation, and temp lighting.
12.1 Block layer delivery, pre-install, and post-install.
12.2 Critical path. Early completion of main electrical room and sequencing.
12.3 Painting walls, columns and selective rooms.
12.4 Multiple scissor lift use in parkade. For timely completion.
12.5 HVAC sequencing.
12.6 Plumbing sequencing.
12.7 Sprinkler, mechanical room, and plumbing tie-in sequencing.
12.8 Genset room sequencing.
12.9 Distribution room sequencing.
12.10 Communication room/security sequencing, fibre/cable backbone, and home runs to floor communication closets.
12.11 Fire caulking, horizontal/vertical.
12.12 Painting metal doors and frames.
12.13 Entry ramp prep, two-ply touch-on, herringbone finish, and trench drain.
12.13a Parkade subtrade final inspections.
12.14 Spray foam pre, install and post-inspection.
12.15 Storage rooms and bicycle storage pre/post review.
12.16 Emergency generator commissioning.
12.17 MUA balancing and parkade exhaust fan balancing review and sign-off.
12.18 Traffic membrane prep, install, safety requirements, and post-inspection.
12.19 Clean out catch basins and sumps, review, and sign-off.
12.20 Pre- and post-pipe protection review and sign-off
12.21 Parkade line painting review pre- and post-sign-off
12.22 Garage door pre- and post-sign-off.
12.23 Pre- and post-building-signage review and sign-off.
12.24 Parkade final inspections.
13.0 STREET LEVEL PRE- AND POST-CANOPY INSTALL.
13.1 Pre-install concrete and envelope review.
Install and post sign-off.
Canopy glass review and sign-off.
14.00 STOREFRONT WINDOW PREP, INSTALL AND POST INSPECTION
Storefront prep, install and post-inspection.
UNDERGROUND SERVICE CONNECTIONS STREET LEVEL.
15.0 Waterworks, domestic, and fire line.
15.1 Storm and sewer.
15.2 Hydro.
15.3 Cable and fibre.
15.4 Natural gas.
STREET LEVEL COMMERCIAL RETAIL UNIT HANDOVERS, CURBS, PARKING METERS AND ASPHALT WRAP-UP.
16.0 Commercial retail unit handovers.
16.1 Planters, stairs, landscaping, and lobby entry.
16.2 Sidewalks, gutter-curbs, parking meters, and street-level wrap-up.
MOST COMMON DOCUMENTATION TO BE SUBMITTED TO CITY OR
MUNICIPALITY FOR FINAL OCCUPANCY. SAMPLE ONLY.
17.0 Action schedule.
17.1 Documents required for submittal.
18.0 SITE REVIEW OF CONSTRUCTION GENERAL COMPLIANCE FOR PRE- OCCUPANCY REVIEW. SAMPLE ONLY
19.0 GETTING READY FOR MAKEUP AIR AND BALANCING TESTING.
20.0 LIFE SAFETY COORDINATED REVIEW TEST PROTOCOL.
20.0 Equipment required.
20.1 Trades required.
20.2 Procedure.
BUILDING LIFECYCLE REVIEW WITH PROPERTY MANAGEMENT
21.0 Review.
LEAN DAILY CONTINUOUS IMPROVEMENT.TOC. SIX SIGMA
BENEFITS. CONSTRUCTION 8 WASTES.
22.0 TOC benefits and lean construction site culture benefits.
22.1 Transportation.
22.2 Motion.
22.3 Waiting.
22.4 Inventory.
22.5 Defects and rework.
22.6 Common over processing defects.
22.7 Underutilization of employees.
22.8 Final overview of lean construction.
23.0 QUALITY CONTROL CHECKLISTS PRE-EXCAVATION TO OCCUPANCY.
23.1 Site start-up checklist.
23.1a Daily construction photo documentation checklist.
23.1b to 23.7 Site trailer supplier and trade meetings checklist.
23.2 Excavation and shoring checklist.
23.3 Metal frames and doors checklist.
23.4 Parkade slab pre-bottom-rebar install, pre-pour, during, and post-pour checklist with added checks for street-level and transfer slabs.
23.5 Vertical forming. Outside walls, inside/outside columns, core, and stairwell.
23.6 Typical slab pre, during, and post-pour checklists.
23.7 Critical path. Electrical room switch gear pre-slab delivery, protection, early ceiling stripping, shoring, safe walkway and early block wall checklist.
23.8 Blockwork pre and post checklist.
23.9 Man-lift erection checklist.
23.10 Man-lift daily use and deliveries.
23.11 Man-lift takedown checklists.
23.12 Plumbers cast and drainage checklist.
23.13 Concrete prep, pre-window and steel stud install checklists.
23.14 Tower window delivery, prep, install, and floor handover
checklists.
23.15 Steel stud layout, install, drop ceilings, con-flow and back framing for subtrade rough-in handover checklist.
23.16 Post subtrade rough-in completion for pre-insulation handover checklist.
23.17 Fire caulking checklist.
23.18 Pre- and post-spray insulation, rigid and batt pre-drywall inspection checklist.
23.19 Levelling floors pre, during, and post checklist.
23.20 Drywall delivery, install, mudding/taping, and pre-painter handover checklist plus temp heating checklist.
23.21 Pre-primer, first coat, and final coat in selected areas.
23.22 Door, doorframe, window stool and door trim delivery/install and post-installation checklist.
23.23 Door doorframe, window stool, door trim, and painters’ spray-out checklist.
23.24 Kitchen cabinet delivery, install, and post-install checklist.
23.25 Floor and wall tile pre- and post-install with backsplash
checklists.
23.26 Countertop measure, delivery, and install checklist.
23.27 Shower glass measure, delivery, install, and post-install
checklist.
23.28 Electrician lighting switches, plugs, and install checklist.
23.29 Laminate flooring pre- and post-install checklist.
23.30 Appliance pre and post-install checklists.
23.31 Plumber and HVAC final fixture install checklist.
23.32 Electrician final fixture install checklist.
23.33 Finishing carpenter final review checklist.
23.34 Final detailing and finish painting checklist.
23.35 Window blind final review checklist.
23.36 Suite cleaning post review checklist.
23.37 Penthouse inside and outside finishing checklist.
23.38 Elevator pre-construction, install, section five and final checklist.
23.39 Man-lift takedown /man-lift suite windows, exterior/membrane and interior completion checklists.
23.40 Flashing and sheet metal checklist.
23.41 Street-level storefront pre and post-install checklist.
23.42 Canopy and canopy glass pre and post-install checklist.
23.43 Preparing for the CRU (commercial retail unit) handover.
23.44 Landscaping pre- and post-planting checklist.
23.45 Common areas checklist.
23.46 Main lobby rough-in to finishing completion checklist.
23.47 Architectural concrete planters and stairs checklist.
23.48 Sidewalks, gutter-curbs, new street lighting, underground electrical conduit install, and parking meter base checklist.
23.49 Key protocol, storage, install and secure handoff. Sequence of construction, real estate, suite and master set. Common areas and utility rooms. Allocation to subtrade foremen entry fobs.
23.50 Pre and post parkade ceiling spray foam checklist
23.51 Pre and post parkade ramp herringbone and trench drain
checklist.
23.52 Parkade traffic membrane sub-surface, during application
and post-application checklists.
23.53 Garage door install and post-install checklist
23.54 Pre and post line painting and pipe protection checklist
23.55 Building signage pre and post-install checklist.
23.56 Window washing protocol during and post-inspection.
1.0 Physical site review.
1.1 Detailed review checklists.
Architectural drawing review.
Structural drawing review.
Mechanical drawing review.
Electrical drawing review.
Landscape drawing review.
Review list for shop drawings.
All of the above to be completed during or before excavation by
consultants, subtrades, and superintendent. This will drastically
cut down on future requests for information.
1.1a Daily construction photo documentation and benefits.
1.1b Bridget construction management mobile app.
1.2 List of suppliers and subtrade meetings to be completed during or before excavation by superintendent.
1.2a Importance of jobsite information flow. Critical path.
1.2b Lean A3 construction problem-solving.
1.3 Work breakdown structure.
1.3a Weekly pull planning.
1.3b Jobsite involvement in construction ergonomics makes good sense.
1.3c On-site and off-site trade prefab.
1.3d Keep jobsite trade teams cooler and warmer.
EXCAVATION AND SHORING
2.0 Excavation and shoring start-up.
2.1 Daily cycles and procedures with extreme weather protocols.
PARKADE FORMING
3.1 Excavation hole and forming organization.
3.2 Shotcrete walls, single-sided and two-sided.
3.3 Other forming system advantages.
3.4 Critical path, early stripping of electrical room and why.
3.5 Parkade slab, pre-pour, during pour, and post-pour checklists,
4.0 CRANE ERECTION
4.1 Pre-erection requirements.
4.2 Pre-operation requirements.
4.3 Pre-climbing requirements
4.4 Pre-dismantling requirements.
4.5 Rigging.
5.0 TOWER FORMING AND SEQUENCING
5.1 Street level.
5.2 Storage.
5.3 Fly form building.
5.4 Five- to six-day forming and subtrade sequencing for typical slabs.
5.5 Accelerated roof completion.
6.0 FLEXIBLE LEAN OFFICES
Move to best tower locations, very important.
6.1 Importance of bi-weekly injury and incident-free meetings by superintendent in addition to weekly safety meetings.
7.0 EXTERIOR MAN-LIFT ERECTION
7.0 General prep and erection.
7.1 Daily effective man-lift use and sequencing deliveries. Critical path.
7.2 Man-lift takedown.
SUPERINTENDENTS INTERIOR SEQUENCING
8.0 Upper tower floor rain diversion during interior rough-in and finishing.
8.0a Plumbers’ drainage and cast.
8.1 Window prep, install, and handover.
8.2 Steel stud layout, erection, drop ceilings, con-flow, and handover.
8.3 Mechanical rough-in and pre-drywall handover.
8.4 Electrical rough-in and pre-drywall handover.
8.5 Backing, fire caulking install, and pre-drywall handover.
8.6 Floor levelling.
8.7 Pre and post spray and rigid insulation install.
8.8 Drywall delivery, install, mudding/taping, and pre-paint.
8.8a Temporary heating suites.
8.9 Paint application and pre-door delivery handover.
8.10 Finishing carpenters install of door frames, doors, door trim, window stools, and selective baseboard for pre-paint.
8.11 Pre-painter spray out. Doors, trim, and window stool.
8.12 Kitchen cabinet delivery, install, and post-install.
8.13 Tile delivery, install, floor and wall sequencing. Post-install.
8.14 Electrician lighting, switches, and plugs.
8.15 Countertop delivery, install and post-install.
8.16 Backsplash install.
8.17 Shower glass and door install.
8.18 Flooring delivery, install, and post-install.
8.19 Appliance delivery, install and post-install.
8.20 Plumber finishing and post-install.
8.21 Electricians’ final pass-through and final.
8.22 Shelving and finishing carpenters final pass-through.
8.23 Final window, balcony slider and balcony exterior door final adjustments.
8.24 Final painter pass-through.
8.25 Protection removal sequencing by well-trained on-site personnel or cleaners.
8.26 First clean of suites.
8.27 Blind install and post-inspection.
8.28 Schedule marketing department walkthrough and key handover.
8.29 Complete second clean pre-home owner walkthrough final.
8.30 Home owner’s first suite inspection.
8.31 Third clean just before move-in day.
8.32 Electrical closets and communication closets.
8.33 Timesavers. Accessories, tools, and simple ways to improve jobsite productivity.
8.34 Penthouse interior and exterior completion.
ELEVATOR DELIVERY, STORAGE, PRE- CONSTRUCTION START-UP AND INSTALL SEQUENCING FINAL.
9.0 Delivery, storage and pre-install.
9.1 Sequence of install.
9.2 Pre-section 5 checklist and pre-final.
9.3 Final.
10.0 INTERIOR COMMON AREAS / LOBBY ROUGH-IN AND FINISHING REVIEW.
10.1 Interior common area rough-in and finishing.
10.2 Main lobby area rough-in and finishing.
10.3 Man lift suites catch-up sequencing.
OUTSIDE TOWER SEQUENCING AND FINISHING
11.0 Roof prep and completion.
11.1 Balcony liquid membrane.
11.2 Window wash anchors and window washing safety.
11.3 Shared exterior swing stages for multiple trade use recommended and why.
11.4 Railing delivery, install, and final.
11.5 Flashing, window, parapet review, and sign-off.
PARKADE SEQUENCING, SHORING STRIPPING THROUGH TO LINE PAINTING
12.0 Stripping, concrete remediation, and temp lighting.
12.1 Block layer delivery, pre-install, and post-install.
12.2 Critical path. Early completion of main electrical room and sequencing.
12.3 Painting walls, columns and selective rooms.
12.4 Multiple scissor lift use in parkade. For timely completion.
12.5 HVAC sequencing.
12.6 Plumbing sequencing.
12.7 Sprinkler, mechanical room, and plumbing tie-in sequencing.
12.8 Genset room sequencing.
12.9 Distribution room sequencing.
12.10 Communication room/security sequencing, fibre/cable backbone, and home runs to floor communication closets.
12.11 Fire caulking, horizontal/vertical.
12.12 Painting metal doors and frames.
12.13 Entry ramp prep, two-ply touch-on, herringbone finish, and trench drain.
12.13a Parkade subtrade final inspections.
12.14 Spray foam pre, install and post-inspection.
12.15 Storage rooms and bicycle storage pre/post review.
12.16 Emergency generator commissioning.
12.17 MUA balancing and parkade exhaust fan balancing review and sign-off.
12.18 Traffic membrane prep, install, safety requirements, and post-inspection.
12.19 Clean out catch basins and sumps, review, and sign-off.
12.20 Pre- and post-pipe protection review and sign-off
12.21 Parkade line painting review pre- and post-sign-off
12.22 Garage door pre- and post-sign-off.
12.23 Pre- and post-building-signage review and sign-off.
12.24 Parkade final inspections.
13.0 STREET LEVEL PRE- AND POST-CANOPY INSTALL.
13.1 Pre-install concrete and envelope review.
Install and post sign-off.
Canopy glass review and sign-off.
14.00 STOREFRONT WINDOW PREP, INSTALL AND POST INSPECTION
Storefront prep, install and post-inspection.
UNDERGROUND SERVICE CONNECTIONS STREET LEVEL.
15.0 Waterworks, domestic, and fire line.
15.1 Storm and sewer.
15.2 Hydro.
15.3 Cable and fibre.
15.4 Natural gas.
STREET LEVEL COMMERCIAL RETAIL UNIT HANDOVERS, CURBS, PARKING METERS AND ASPHALT WRAP-UP.
16.0 Commercial retail unit handovers.
16.1 Planters, stairs, landscaping, and lobby entry.
16.2 Sidewalks, gutter-curbs, parking meters, and street-level wrap-up.
MOST COMMON DOCUMENTATION TO BE SUBMITTED TO CITY OR
MUNICIPALITY FOR FINAL OCCUPANCY. SAMPLE ONLY.
17.0 Action schedule.
17.1 Documents required for submittal.
18.0 SITE REVIEW OF CONSTRUCTION GENERAL COMPLIANCE FOR PRE- OCCUPANCY REVIEW. SAMPLE ONLY
19.0 GETTING READY FOR MAKEUP AIR AND BALANCING TESTING.
20.0 LIFE SAFETY COORDINATED REVIEW TEST PROTOCOL.
20.0 Equipment required.
20.1 Trades required.
20.2 Procedure.
BUILDING LIFECYCLE REVIEW WITH PROPERTY MANAGEMENT
21.0 Review.
LEAN DAILY CONTINUOUS IMPROVEMENT.TOC. SIX SIGMA
BENEFITS. CONSTRUCTION 8 WASTES.
22.0 TOC benefits and lean construction site culture benefits.
22.1 Transportation.
22.2 Motion.
22.3 Waiting.
22.4 Inventory.
22.5 Defects and rework.
22.6 Common over processing defects.
22.7 Underutilization of employees.
22.8 Final overview of lean construction.
23.0 QUALITY CONTROL CHECKLISTS PRE-EXCAVATION TO OCCUPANCY.
23.1 Site start-up checklist.
23.1a Daily construction photo documentation checklist.
23.1b to 23.7 Site trailer supplier and trade meetings checklist.
23.2 Excavation and shoring checklist.
23.3 Metal frames and doors checklist.
23.4 Parkade slab pre-bottom-rebar install, pre-pour, during, and post-pour checklist with added checks for street-level and transfer slabs.
23.5 Vertical forming. Outside walls, inside/outside columns, core, and stairwell.
23.6 Typical slab pre, during, and post-pour checklists.
23.7 Critical path. Electrical room switch gear pre-slab delivery, protection, early ceiling stripping, shoring, safe walkway and early block wall checklist.
23.8 Blockwork pre and post checklist.
23.9 Man-lift erection checklist.
23.10 Man-lift daily use and deliveries.
23.11 Man-lift takedown checklists.
23.12 Plumbers cast and drainage checklist.
23.13 Concrete prep, pre-window and steel stud install checklists.
23.14 Tower window delivery, prep, install, and floor handover
checklists.
23.15 Steel stud layout, install, drop ceilings, con-flow and back framing for subtrade rough-in handover checklist.
23.16 Post subtrade rough-in completion for pre-insulation handover checklist.
23.17 Fire caulking checklist.
23.18 Pre- and post-spray insulation, rigid and batt pre-drywall inspection checklist.
23.19 Levelling floors pre, during, and post checklist.
23.20 Drywall delivery, install, mudding/taping, and pre-painter handover checklist plus temp heating checklist.
23.21 Pre-primer, first coat, and final coat in selected areas.
23.22 Door, doorframe, window stool and door trim delivery/install and post-installation checklist.
23.23 Door doorframe, window stool, door trim, and painters’ spray-out checklist.
23.24 Kitchen cabinet delivery, install, and post-install checklist.
23.25 Floor and wall tile pre- and post-install with backsplash
checklists.
23.26 Countertop measure, delivery, and install checklist.
23.27 Shower glass measure, delivery, install, and post-install
checklist.
23.28 Electrician lighting switches, plugs, and install checklist.
23.29 Laminate flooring pre- and post-install checklist.
23.30 Appliance pre and post-install checklists.
23.31 Plumber and HVAC final fixture install checklist.
23.32 Electrician final fixture install checklist.
23.33 Finishing carpenter final review checklist.
23.34 Final detailing and finish painting checklist.
23.35 Window blind final review checklist.
23.36 Suite cleaning post review checklist.
23.37 Penthouse inside and outside finishing checklist.
23.38 Elevator pre-construction, install, section five and final checklist.
23.39 Man-lift takedown /man-lift suite windows, exterior/membrane and interior completion checklists.
23.40 Flashing and sheet metal checklist.
23.41 Street-level storefront pre and post-install checklist.
23.42 Canopy and canopy glass pre and post-install checklist.
23.43 Preparing for the CRU (commercial retail unit) handover.
23.44 Landscaping pre- and post-planting checklist.
23.45 Common areas checklist.
23.46 Main lobby rough-in to finishing completion checklist.
23.47 Architectural concrete planters and stairs checklist.
23.48 Sidewalks, gutter-curbs, new street lighting, underground electrical conduit install, and parking meter base checklist.
23.49 Key protocol, storage, install and secure handoff. Sequence of construction, real estate, suite and master set. Common areas and utility rooms. Allocation to subtrade foremen entry fobs.
23.50 Pre and post parkade ceiling spray foam checklist
23.51 Pre and post parkade ramp herringbone and trench drain
checklist.
23.52 Parkade traffic membrane sub-surface, during application
and post-application checklists.
23.53 Garage door install and post-install checklist
23.54 Pre and post line painting and pipe protection checklist
23.55 Building signage pre and post-install checklist.
23.56 Window washing protocol during and post-inspection.
About The Book
Lean Construction
Concrete Tower Sequencing, Pre-Excavation To Occupancy, Superintendents Perspective By Mark S. Heeres A high percentage of construction projects have budget and cost overruns. Productivity has flatlined in the last fifty years. Costly rework and defects are common. Lean construction is the bringing together and the respect for all jobsite team members. Built on trust, fairness and honesty. Helping every jobsite team member with skill development and growth. Recognizing and rewarding their improvements. By eliminating waste and adding value, Lean will produce safer jobsites, uninterrupted trade handovers, better quality and schedule reliability. Down to earth collaboration between owners, architects, consultants and site personnel. Working together towards a quality tower handover to the suite owners, developers and general contractors.
|